Skip to main content

Dewatering from excavation pit.

 




What to do if the excavation pit is waterlogged? Or what are the procedures you have to follow for dewatering the excavation pit? All these things seem to be minor, but actually not so. You have to take a long step to do it, and also have high thinking. You already know, how waterlogging occurs. Due to heavy rainfall or continuous rainfall, the area gets flooded and thus waterlogging occurs. But what happens, if your construction site or the excavation you have done for RE Wall gets waterlogged? So there are various steps you should have to do as follows: 

First of all, you cannot do dewatering directly if you see the water level rising up to the ground surface. You have to wait for some days for the sun to appear and to evaporate it. After that you can bring the water pump to dewater the excavation pit. Since the Sun cannot evaporate all the flooded water at once. It will need days to evaporate it or even a week. 
And if the sun appears one-or-two days and again the rainfall occurs, then it will be the same condition as before. So for these you have to wait till the flooded water lowers down/evaporates up. And when the water level is below the water table then ready for dewatering work. 


Second, for dewatering work, you have to do one step before. If any cement bags or sack bags are there, or left out anywhere throwing after use, you put some sand in it. So that you can put it them layer by layer or even barrier by barrier. So that you can dewater it part-by-part. Like this 



At last, you can go for dewatering work. It becomes easy and efficient. You find the way about the outlet, where the dewatering water would go/where to settle it. 

So all this process were followed in my site. The whole ground was heavily flooded and the water cannot pass through it. So with this flooded water the curing work was done on the panels and also it became use for washable concrete mixtures. But the excavation pit was dumped down like as river. And later when the water soaked or evaporated during sunny day, the dewatering work was on process.

So, like this process the work is going on and dewatering work is also on process. The amount of water fill there, will take minimum one week to clear it. So dewatering work will be going on continuously. In all construction process it's different. But here the process took long to dewater it. 
Also in building construction the process is different, in dam construction different process is used to dewater it, in construction of bridge & tunnels also. 
But here for RE Wall, as the excavation pit is too large and also the depth is more, so longer process it took to dewater it. You have to make a barrier with sack bags, make them part-by-part, then do dewatering etc. & etc. 


Comments

Popular posts from this blog

MACHINES USED AT CONSTRUCTION SITES

 The most commonly used machine at any construction site is JCB where it's technical name is Backhoe. It is the most common and widely used machine in any construction project whether its big or small project. It becomes easier and makes the work faster for the companies at any time of interval.    All other machines such as Transit Mixer, Concrete Mixer, Roller etc are also used in any kind of road project or building project. Transit Mixer is used for large large building projects, bridge projects, some kind of road projects etc. whereas concrete mixer is for small building projects. Roller is used for road project and bridge project for its elevation.  For any building project the most commonly used machines are concrete mixer, transit mixer, concrete pump, bar bending machine, needle vibrator, water pump and many more. All these machinery works make the work easier and faster. Otherwise if the work is done with labourers it will take more time and less efficient for the work. 

How to edit grid systems in Etabs

 Okk in the last blog I had discussed about Etabs for beginners. You have got at least some ideas about it. If you have not seen it then click here . But here I am going to discuss how you will edit Grids/Columns in Etabs. As I had said by clicking on "Modify/Show Grid Systems" option a new dialog box appears, their you can edit anything. But you can also do it by different way. On the left side in grid dimensions (plan) you can see that two options are available. One is "Uniform Grid Spacing" and the other is "Custom Grid Spacing". Click on the "Custom Grid Spacing" and you see that Edit Grid Data option is available. Just click on that, and you can edit it as you want by giving the required dimensions in X-axis and Y-axis only. Ok whatever be lets come to the topic. If you have done it like as I have shown earlier then follow those steps. And the one who were new to this blog this is just for that. That's why I underlined with BLUE line an

Excavation for RE Wall.

 So, hey guys! How are you? You might have read my previous blogs about panel casting  and panel placing . Now it's time to learn about panel erection or what to do after 3-4 months of casting the panels. So the first step is about excavation for RE Wall. Then only you can erect the panels. So let us learn about this excavation part.  You all know excavation work is done by JCB or Falkland. To excavate the soil and then carry it to the other dumped areas. But before excavation you all know, to marked the center line as well as the outer line also so that the area doesn't excavate much as per the requirement. For excavation just you need to take 500mm more, then that of the given drawing.  Doing this excavation is easy. But what to do if it's flooded with rain water/ or water coming from other sources. Definitely your answer will be to do dewatering work with a water pump. That's fine. But do this dewatering work with almost by fixing 3-4 water pumps. So that it soaks mo