Skip to main content

PLACING OF CONCRETE AND ITS MIXING

 There are some skills that are need to be gained by site engineer, contractor and mistry as well as the site supervisor. They must be aware and conquer about the cure of concrete. There are some certain issues which are to be faced during placing of concrete. 

       (a) First of all the reinforcement should be checked whether the nominal cover or clear cover is given or not. Otherwise this will lead to the rusting of reinforcement which will caused due to its atmospheric effect when water or muddy soil will enter into the pores or voids of the concrete. 

      (b) The next typical thing is that the shuttering should be checked whether it is straight or not or according to the drawing is given or not, max. end to end distance is provided or not. Because after pouring the concrete it will not be possible to adjust or remake it. Therefore all things should be checked before placing of concrete. 

      (c) The most important thing is that, the vibrator must be their at the site. Without vibrator the placing of concrete is of no use. It will lead to honeycomb like structures and failure of concrete. Therefore after placing of concrete upto the brim level the vibrator must be used. 

HOW  TO  MIX  THE  CONCRETE

One of the most important thing is that the workers dosen't know how to mix the concrete. They think that they are the most experts in mixing the concrete but can't identify the ratio in what order to mix. For PCC the ratio is 1:3:6 and for RCC the ratio is 1:1.5:3 and above this is also given but the given ratio is for building works or dam works. 

But before doing any concreting work first of all cube test should be done. It should be in the ratio 1:1.5:3. It is placed in the cube mould and after that it is taken in the lab for testing. 


Moreover the further placing of concrete is to be done in a systematic manner or lucent manner. Otherwise there will be faulty in any case of concreting work. Be careful with mistry, contractor and supervisor. They think themselves to be the best because of experience in all this type of works. But the main technical term of this work is dosen't known by them. Neither they know the use of vibrator nor the mixing of aggregates as per w/c ratio. 

Comments

Popular posts from this blog

How to edit grid systems in Etabs

 Okk in the last blog I had discussed about Etabs for beginners. You have got at least some ideas about it. If you have not seen it then click here . But here I am going to discuss how you will edit Grids/Columns in Etabs. As I had said by clicking on "Modify/Show Grid Systems" option a new dialog box appears, their you can edit anything. But you can also do it by different way. On the left side in grid dimensions (plan) you can see that two options are available. One is "Uniform Grid Spacing" and the other is "Custom Grid Spacing". Click on the "Custom Grid Spacing" and you see that Edit Grid Data option is available. Just click on that, and you can edit it as you want by giving the required dimensions in X-axis and Y-axis only. Ok whatever be lets come to the topic. If you have done it like as I have shown earlier then follow those steps. And the one who were new to this blog this is just for that. That's why I underlined with BLUE line an...

How to make Staircase in Etabs

 In the last blog I had described about making beams, columns, slabs/roofs in Etabs. But I forgot to tell you how to make staircase. Apology for that. But today in this blog I am going to discuss how to make staircase in Etabs. So before making Staircase first of all delete one side of the slab by single click. But remember one thing in the story side you should have to click "All Stories" so that automatically all slabs will get deleted and required gap and positioning will be appeared.  First click on All Stories After that select one portion of slab   After that go to Edit menu and click on Delete   Then one part of the slab of each story becomes hollow So doing the following steps you can now make the staircase. As for staircase we need hollow section at the top of it, so that it's free to move. In practical field also you can't provide staircase if the roof is covered with slab. Now the main procedure begins for Etabs.  Go to define tab menu and click on Se...

WHAT IS PEDESTAL IN FOOTING ?

 During foundation you should always be careful that there is no water present in the excavation pit and the depth should be accurate. So for that you need manwork and labourers to maintain it's accuracy. So before going further for any work just be careful that the depth of foundation is accurate and no error should be made. Because the structure of a building is fully depend upon foundation. And this is general sense that the all the building loads are carried to the foundation i.e., footing.  Before doing any foundation work first of all brick soiling is to be done or sand filling. The building where high rise structures are made, sand filling is done; but the house with ground floor, brick soiling is sufficient. But from where you will get the bricks. Obviously you will have to order or bring it from bricks factory where bricks are made. And after bringing the bricks where you will placed them?  (Actually all these practical knowledge are not taught in the college so ...